Cayman’s utilities regulator has approved a proposal by power firm CUC to add more generation capacity in a bid to avoid blackouts — but with fossil fuels rather than green energy.

Officials at the Utility Regulation and Competition Office, known as OfReg or URCO, said the decision was based on CUC’s failure to abide by the terms of its transmission and distribution licence in its application.

But CUC hit back that OfReg had allowed one of four proposals that would be most expensive for the consumer — and one that would “perpetuate reliance on fossil fuels as the primary generation source for Grand Cayman’s energy future”.

The row broke out after CUC last summer submitted four different plans to the regulator as part of what was treated as a “certificate of need” (CON) to boost power production.

Samuel Jackson, OfReg chairman, said, “This process took much longer than would ordinarily be necessary because CUC’s submission included alternative proposals for generation which failed to meet both the terms of its transmission and distribution licence and the prescribed format for a certificate of need as set out in CUC’s main agreement.

- Advertisement -

“Despite this, given the now urgent need to address grid stability, which is due to the
failure of CUC in previous years to submit a CON in accordance with its licence, the
Board decided to treat CUC’s submission as a certificate of need.”

OfReg said the CUC proposal that was approved was for 90.1 megawatts (MW) of new thermal, firm, capacity, which will be open to bidders, including CUC.

The three others were a blend of firm capacity and standalone solar generation, a mix of firm and hybrid solar-plus-storage generation, and a combination hybrid solar-plus-storage with no new firm generation.

The regulator said none of the rejected proposals were in line with CUC’s transmission and distribution licence, as they included “a component of non-firm renewables generation”.

It added that the board was “constrained by CUC’s licence and the legislative framework to only authorise the one option in the proposal for electricity generation which conforms to
CUC’s licence, namely the option of 90.1MW of firm generation”.

The regulator explained, “In so doing, we were mindful of our duty to protect the public interest by, inter alia, promoting competition in electricity generation, in accordance with the relevant statutory provisions and CUC’s generation licence.”

CUC: Preferred option not chosen

But CUC said its preferred option was for 100MW of large-scale solar power, plus battery storage and and 36MW of thermal generation.

“This option would ensure the delivery of reliable and safe service, position renewable energy as the primary source on the grid and offer significant cost savings to customers,” a CUC spokesperson said.

“OfReg has chosen to decline this proposal in favour of the business-as-usual scenario of 90 MW of thermal generation.”

But OfReg insisted the decision, which will mean a request for proposal to supply the extra power, for which CUC and other qualified bidders can compete, did not mean it had turned its back on renewable energy.

Sonji Myles, OfReg’s interim CEO, said, “CUC’s own submissions makes the distinction between firm and hybrid generation clear.

“If CUC believes it is time to redefine what qualifies as firm capacity, that requires a formal, transparent process to amend the licence – not a request to reinterpret it midstream to fit a preferred outcome.”

A spokesman for the regulator added, “URCO [OfReg] also wishes to dispel any perception that this determination is a step back from renewable energy adoption.”

He added that OfReg was “just weeks away” from the launch of a request for proposal for the biggest-ever renewable energy solicitation project.

“This is not a rejection of renewables,” Myles said, “it is a defence of process and fairness. We are already advancing a 22.5 MW renewable dispatchable solar-plus-storage project through a competitive process and more will follow later this year.”

‘Shifting the blame’

James Whittaker, president of the Cayman Renewable Energy Association, told the Compass, “It is unfortunate that we are in a position where we are replacing fossil fuel generation with more fossil fuel generation in 2025, however, the source of this problem originates with CUC and not the regulator.

“For years CUC has attempted to diminish the growth of third-party-owned renewable energy systems, which would have helped to avoid the grid problems they’re experiencing now.”

Whittaker added that it was only because of the 2024 national energy policy that the country could sort out problems in the future.

“While none of this materially affects Cayman’s renewable energy goals under the new policy, given it’s largely just a replacement of existing generation, unfortunately, the new policy is too little too late to impact the current need at hand,” he said.

Whittaker added that CUC seemed to be trying to “shift the blame to the regulator” for not resolving the problem.

But he highlighted that “the regulator has to follow the law and CUC has been trying to have the regulator approve a large utility-scale solar farm without any competitive bid process — which is in violation of the law — for years now.”

He continued, “In simple terms, CUC created the problem through their own actions and is in effect asking the regulator to approve a project that would circumvent the law in order to remedy a problem they themselves created.

“The regulator has said ‘no’ to doing so and it appears CUC is now trying to paint them as anti-renewables and making a poor choice for Cayman in not gifting the monopoly utility the right to build solar farms without any competitive bid process at all.”

3 COMMENTS

  1. I have been a developer of Residential Solar projects since 2007.
    What is disgusting, is the CUC Fuel Charge put against the solar power generated by a residential customer! The residential solar power generated by their own equipment should not be taxed with a CUC FUEL Charge!
    The residential customers invested and paid for their own solar equipment and their KW of power they generated should NOT be taxed with the CUC Fuel charge!

  2. To clarify the partial quote published.

    There are two issues at play related to competition and this matter.

    1) CUC asking the regulator to approve non competitive solar farms for them, which OfReg themselves said is not legal and which is well documented. 2) CUC having positioned themselves to gain unfair competitive advantages over the rest of the market in the coming RFPs for solar farms. Which is also well documented and we’ll see if it’s legal as well.

    JW

  3. Everyone is trying to push their angle, so I have conducted my own research. Below is what I have found out and I hope it helps people understand what the debate is about.

    1) CUC asked OfReg in 2021 if they could build a solar/battery to meet the growing use of electricity. OfReg agreed on the need for new generation but declined CUC’s proposal to build it since any generation built needs to be competitive tendered. OfReg announced in 2021 that they would run this tender for the large scale solar.
    2) Fast forward to 2025 and OfReg has not issued the tender for the solar/battery plant.
    3) Electricity usage has grown and with no new generation I am led to believe that there is only just enough generation to supply the current usage (Ref to CUC press release in 2024 stating things were tight). I am guessing that if the solar/battery system had been tendered back in 2021 then it would have been operating by now and we could have avoided being in this tight spot.
    4) CUC submitted a report to OfReg last year with options for generation to meet the future electricity usage needs. The options included just thermal, thermal and solar/batteries, and just solar/batteries. Their recommendation asked OfReg to approve a mostly solar/battery solution with a small amount of thermal (100mw Solar and 36mw thermal). Any new generation will be tendered by OfReg and according to law is an open competitive process. The report was reviewed by an independent consultant who noted that the methodology used aligned with best practice and made further recommendations to improve it.
    5) OfReg announced that they could not approve any of the solar options since CUC were not allowed within the wording of their license to suggest any option that were not thermal.
    6) Progressing the proposed renewable option would have reduced emissions and reduced the cost to consumers by $20-25 million per year.
    6) The National Energy Policy was revised in 2023 setting clear guidance on reducing emissions and renewable energy targets for Cayman.

    The above are the facts I have found. What I have not been able to find out includes:

    1) Why the solar/battery proposed in 2021 has taken more than four years for OfReg to tender, which has led to the country possibly facing an electricity shortfall.
    2) Why CUC doesn’t clearly point out that they were reliant on OfReg progressing the 2021 tender to have sufficient generation.
    2) Why OfReg did not consult on a change to the CUC license to allow for a renewable option to be progressed. This appears to go against the whole intent of the National Energy Policy. Any new thermal built will be here for the next 20-30 years and will cost us consumers $25m more a year compared to a renewable option.
    4) Why the various bodies in the industry don’t get together to discuss how they can work together to get things done. The President of CREA just bags CUC and OfReg and appears accepting of new thermal generation rather than promoting renewable energy, and CUC and OfReg just bag each other.
    5) Who is going to help sort this out? I would like cheaper electricity from renewables since my cost of living is already too high.